No alarm interface to ED.00.08
Boxing in required to Salto box for security
ESH.G.07- Dado trunking already installed outside contract- therefore to be omitted from scope
Ditto
Intumescent strips required to Plant door ED.00.01. Door also sticking
New recessed manhole cover- setting/ infill to be redone- currently trip hazard on escape route
COI item- board over existing duct where pigeon nesting
Taping and jointing complete to Basement- awaiting hatch to gas meter location
Escape signage complete to basement
1 No. edge bead incomplete on stair to basement
New stair nosing required- to be fitted- basement stair
Redundant light fitting to Stair 1 SH.G.04 to be removed/ replaced with L4E emergency fitting
Nosings to be cut back/ burr removed to winder Stair 1 SH.G.05
School Bell to be removed/ replaced with other alarms in Chapel
Ditto- break glass to be removed/ sounder also/ decorations to be made good following chapel fire alarm installation
Window to SH.G.12- fireboard to be reinstated + fire batt/ intumescent foam around service penetrations- COI required
Conduit/ wall to be made good SH.G.09
Decorations to be made good where services removed- SH.1.07 adjacent ID.01.06
Ditto
Cable to be removed following chapel alarm installation. bulkhead to be made good adjacent conduit
Data faceplate complete to dado ESH.1.01
Make good conduit ESH.1.06
Ditto
Make good wall/ decs to meeting room
Friday, 28 February 2014
Monday, 24 February 2014
Site Visit 21.02.14
Store SH.G.13. Existing cill raked. HRW to forward revised detail
Coping to bay window condemned. Coping to be redone. Cutting/ pointing/ overhang defective. B&H to recut/ reset.
Ditto
Shoe required to downpipe- into gulley
ED.00.03- Decoration still required
Bulkhead to courtyard- COI required for boarding over of bulkhead.
Paving to courtyard. Further cuts/ infill required to perimeter
Bend/ shoe required for boiler condensate to new gulley
Inset cover to manhole to be reset- currently trip hazard on fire escape route
Remaining stray cables to be trimmed. loose felt to be trimmed above EW.1.04
Brick pavers to be cleaned fully of cement/ debris
Handrail now fitted to stair of Lobby ESH.1.02- COI to be raised
Bulkhead to be completed with T&G/ shiplap as H21/ 110A. Additional lead flashing required over- COI required.
CBD door ID.02.05- make good decs where escutcheon removed
Cable to be removed following installation of new bell system
Window EW.02.03 not decorated externally. Ditto EW.01.29, EW.01.30
trunking/ redundant cables to be removed/ decorations made good to 2FL stair- Stair 2
Ditto
Basement- taping and jointing still required
Ditto
New nosings to timber access stair still to be fitted
Photocopier in Disabled refuge area
IW.00.01- services penetration to be fire stopped- also fire-rated board over existing window- as raised by Fire Officer. COI to be raised if not part of original scope/ or if removed within contract.
Coping to bay window condemned. Coping to be redone. Cutting/ pointing/ overhang defective. B&H to recut/ reset.
Ditto
Shoe required to downpipe- into gulley
ED.00.03- Decoration still required
Bulkhead to courtyard- COI required for boarding over of bulkhead.
Paving to courtyard. Further cuts/ infill required to perimeter
Bend/ shoe required for boiler condensate to new gulley
Inset cover to manhole to be reset- currently trip hazard on fire escape route
Remaining stray cables to be trimmed. loose felt to be trimmed above EW.1.04
Brick pavers to be cleaned fully of cement/ debris
Handrail now fitted to stair of Lobby ESH.1.02- COI to be raised
Bulkhead to be completed with T&G/ shiplap as H21/ 110A. Additional lead flashing required over- COI required.
CBD door ID.02.05- make good decs where escutcheon removed
Cable to be removed following installation of new bell system
Window EW.02.03 not decorated externally. Ditto EW.01.29, EW.01.30
trunking/ redundant cables to be removed/ decorations made good to 2FL stair- Stair 2
Ditto
Basement- taping and jointing still required
Ditto
New nosings to timber access stair still to be fitted
Photocopier in Disabled refuge area
IW.00.01- services penetration to be fire stopped- also fire-rated board over existing window- as raised by Fire Officer. COI to be raised if not part of original scope/ or if removed within contract.
Friday, 7 February 2014
Site Visit 06.02.14
ESH.1.01- decorations underway- light installation underway- drops to be extended to allow fittings to be below beam level
ESH.1.05 Meeting room- data cable installation complete- containment has not been provided
SH.2.10- remove switch and all other redundant cabling
Exams Paper store SH.1.10- Picture rail mismatched
SH.1.11 Exams Office- make good decs
Make good under emergency light fitting to stair adjacent ID.01.17 (outside exams office)
Evidence of water ingress over window EW.00.08 to Paper Store SH.G.15
Main Door ED.00.05 now painted, ironmongery fitted.
Make good/ redec around all areas internally where emergency light fittings and sounders are removed in lieu of new installations
Decorate or box around existing pipes to Database Office SH.G.09
Existing carpets retained- require builders clean
Redecorate to all areas where door closers have been installed
ESH.1.05 Meeting room- data cable installation complete- containment has not been provided
SH.2.10- remove switch and all other redundant cabling
Exams Paper store SH.1.10- Picture rail mismatched
SH.1.11 Exams Office- make good decs
Make good under emergency light fitting to stair adjacent ID.01.17 (outside exams office)
Evidence of water ingress over window EW.00.08 to Paper Store SH.G.15
Main Door ED.00.05 now painted, ironmongery fitted.
Make good/ redec around all areas internally where emergency light fittings and sounders are removed in lieu of new installations
Decorate or box around existing pipes to Database Office SH.G.09
Existing carpets retained- require builders clean
Drainage underway for external downpipe