Monday, 28 October 2013
Site Visit 24.10.13
Bursar's office- skirting to be cut back to allow trunking to be fixed directly to wall- to avoid existing floor joist.
Cupboard door ironmongery difficult to fit- CVA to liaise with AC Leigh regarding their specification
Doors 1st floor routed in lieu of smoke seals
Windows to former flat now awaiting secondary glazing- all squaring of openings to be carried out by Selectaglaze. Decorations may need to be made good following installation.
Straps to 2FL roof installed- between rafters and flank walls
Purlin prop plates now installed to 2FL- roof structure
Ditto
Asphalt kerb now extended to 150mm height minimum- awaiting parapet flashing
Dormer flashings underway to Ingrave Road elevation
2FL spine wall- battens installed for drylining finish
Dormer flashing to rear elevation. Tiling awaiting completion/ render to cheeks to be completed
Dormer flashings- soakers awaiting render to cheeks over- render bead to be applied
Dormer lead detail
Existing leadwork adjacent chimney to be dressed back over lead soakers
Straps to spine wall 2FL
Valley awaiting flashing/ tiling.
Single outlet blocked- new outlets drilled- in compliance with lead sheet association recommendations
Back of lead dormer completed
Damage to solid balustrade- to be made good prior to decoration
TRVs required to radiators within archive room
Awaiting new solid balustrade detail to 2FL service stair
AC Leigh wired door access readers fitted
Awaiting bulkhead to be constructed- Director MIS office
6mm ply currently being fitted to 1FL offices
Cupboard door ironmongery difficult to fit- CVA to liaise with AC Leigh regarding their specification
Doors 1st floor routed in lieu of smoke seals
Cornice to be adjusted to ensure meeting at corner/ mitre
Windows to former flat now awaiting secondary glazing- all squaring of openings to be carried out by Selectaglaze. Decorations may need to be made good following installation.
Straps to 2FL roof installed- between rafters and flank walls
Purlin prop plates now installed to 2FL- roof structure
Ditto
Insulation installed between valley deck and valley steel as specified
Dormer flashings underway to Ingrave Road elevation
2FL spine wall- battens installed for drylining finish
Dormer flashing to rear elevation. Tiling awaiting completion/ render to cheeks to be completed
Dormer flashings- soakers awaiting render to cheeks over- render bead to be applied
Dormer lead detail
Existing leadwork adjacent chimney to be dressed back over lead soakers
Straps to spine wall 2FL
Valley awaiting flashing/ tiling.
Single outlet blocked- new outlets drilled- in compliance with lead sheet association recommendations
Back of lead dormer completed
2FL soft strip/ demolition completed. Stair opened up
TRVs required to radiators within archive room
Awaiting new solid balustrade detail to 2FL service stair
AC Leigh wired door access readers fitted
Tuesday, 15 October 2013
Site Visit 14.10.13
1st fix electrical tray/ builderswork
Plastering skim coat to Accounts Archive SH.2.12
Ditto
Builderswork/ electrical containment route underway high level 2nd floor
HR Office mist coat completed but redundant cables/ services require removal
Ditto
Ditto
Where TRV fittted cill poorly cut- to be rectified
Window refurbishment to be completed
Rafters and purlin prop require decoration following plasterboard lining completion. CVA to forward proposal
Valley beam steel/ timber connections
Felt/ battening underway
Gutter requires amended kerb adjacent parapet. Overall height from lowest level of gutter should be 150mm minimum and upstand formed in 18mm as K11/ 515A. Asphalt/ kerb to be independent of parapet wall by 10mm as in clause K11/515A. Lead flashing to be dressed over- thermal movement to be allowed between two structures. Contractor to amend prior to an further leadwork.
Internal frame of dormer
External ply cladding to dormer
Dormer detail awaiting lead
GFL- electrical containment extends beyond line of wall above/. External weatherboarding detail to be amended to accommodate. 90 degree turns at limits.
GFL Lobby SH.G.16 ceiling to be amended to accommodate revised electrical services opening/ route to left hand side of existing heating pipework.
Outlet location to be amended in accordance with LSA.
Awaiting hopper to 2FL outlet through wall
Plastering skim coat to Accounts Archive SH.2.12
Ditto
Builderswork/ electrical containment route underway high level 2nd floor
HR Office mist coat completed but redundant cables/ services require removal
Ditto
Ditto
Where TRV fittted cill poorly cut- to be rectified
Window refurbishment to be completed
Rafters and purlin prop require decoration following plasterboard lining completion. CVA to forward proposal
Valley beam steel/ timber connections
Felt/ battening underway
Gutter requires amended kerb adjacent parapet. Overall height from lowest level of gutter should be 150mm minimum and upstand formed in 18mm as K11/ 515A. Asphalt/ kerb to be independent of parapet wall by 10mm as in clause K11/515A. Lead flashing to be dressed over- thermal movement to be allowed between two structures. Contractor to amend prior to an further leadwork.
Ditto
Internal frame of dormer
External ply cladding to dormer
Dormer detail awaiting lead
GFL- electrical containment extends beyond line of wall above/. External weatherboarding detail to be amended to accommodate. 90 degree turns at limits.
GFL Lobby SH.G.16 ceiling to be amended to accommodate revised electrical services opening/ route to left hand side of existing heating pipework.
Outlet location to be amended in accordance with LSA.
Awaiting hopper to 2FL outlet through wall