Wednesday, 2 October 2013

Site visit 01.10.13

 Dormers under construction- vent details discussed.

 25mm to be allowed between lead drip and face of render- insect mesh to be fitted

 Cheeks to be built of 12mm WBP to maintain 25mm gap

 Rafters propped prior to new purlin installation

 Basement- screed/ membrane/ sump/ pump installed

 Basement- brick wall to be rebuilt to Ingrave Road elevation/ remainder of membrane applied

 Window decoration underway- scaffold erected through existing canopy