Tuesday, 17 December 2013

Site visit 16.12.13

 SH.G.07 Common Room Secretaries- Lighting rose/ cabling to be modified

Ditto

 
 Door decoration/ ironmongery/ closer/ signage to be completed asap- Phase I works incomplete

 Making good required to plaster/ decs

 Phase II- Database Office SH.G.09- containment strategy discussed with M&E Solutions

 RWP route/ outlet to be instructed to SH.G.08 high level. Historic leak/ no fall/ no rodding access to current high level pipe. CVA to instruct


 RWP- to be replaced

 Hopper high level to light well. Calc of rainwater into lightwell required- CVA

 Redundant gas pipe to be removed to basement area

 Ceiling nearing completion GFL SH.G.06 Director MIS. Switchover of power to happen after Weds 18th as connected to Reprographics

 Ceiling- Ditto

 Repair to pipe- Mech subcontractor to forward spec of pipe clamp-

Trunking to SH.2.12- still to be made good/ redundant cabling to be fully removed.

Friday, 13 December 2013

Site visit 12.12.13

School House- scaffold almost struck- Ingrave Road

New RWP required with rodding access- within Hall SH.G.08

Ditto- route/ size to be reviewed with OR consulting on Mon 16.12

Phase II SH.G.09 works commenced

Ditto

Electrical containment strategy discussed to feed access control

Crack to Exams Office SH.1.11

Ditto- HRW to forward details of remedial works required

Opening formed, Door/ doorset ID.01.16 installed

Internal window to SH.1.10 blocked up

Door to SH.1.10 blocked in
Riser to SH.1.10 exposed
Stair 2 to plant area decorated- awaiting handrail

Smoke seal/ ironmongery/ signage to be fitted to cupboard door ID.02.05

SH.2.10 to be completed- decs etc.

Dado to Archive store SH.2.12 to be completed- walls/ ceiling touched in

cill to ID.01.08- diminishing strip required

Hoppers/ downpipe fitted to lightwell

Velux rooflights to top floor operational- awaiting fitting of blinds

Steel exposed to SH.G.15. Remdial works required to adjacent room SH.G.13

Friday, 6 December 2013

Contractor Site Photos 06.12.13

 Temporary fire alarm installed 1FL

 Temporary fire alarm installed 2FL

 Door signage/ fire signage installed

 Fire signage installed

 Guarding installed to 2FL landing, carpet/ nosings/ Part M handrail installed

 Carpet/ nosings/ Part M handrail installed

 Carpet/ nosings/ Part M handrail installed

Wednesday, 4 December 2013

Site Visit 02.12.13

 Lining paper to cbd SH.1.06- make good/ redec

 Ditto
 Trunking SH.1.06- Make good dec/ mastic dado

 Reinstate carpet SH.1.06

 Radius to conduit/ bulkhead SH.1.06 to be rectified

 Decoration adjacent ID.01.19/ dado- complete

 Complete carpets 1st floor

 Ditto

 Remove redundant cables to picture rail SH.1.04

 SH.1.01- address mortar/ carpet tile/ skirting interface

 Cap dado adjacent fireplace SH.1.01

 Make good junctions to dado trunking SH.1.01

 Ditto

 SH.2.06- nearing completion

 SH.2.06- Mastic to boxing in
 SH.2.06- Complete decs adjacent dado/ door

SH.2.02- 2nd coat to rooflight lining  required

 SH.2.02-crack below purlin- M/G redec

 SH.2.02- dado interface- redo

  SH.2.02- Decorate behind purlin

 Temp alarm install phase I/ complete system phase II

 Complete Sikkens decorations to exposed purlins/ purlin props 2FL

 Install guarding SH.2.04

 Install handrail- Part M compliant- Stair 1

 Clip cables to rooflight- all 2FL

 All carpet/ nosings to stair 1 complete

 Make good decs to stair 1

 Exposed threads to conduit SH.2.04

 Complete ironmongery installation EW.01.05

 SH.1.05- install grille to wall

 SH.1.05-complete dado
 Ditto

 SH.1.05-complete door decs ID.01.04

 Stair 1 soffitt 1FL to GFL- make good/ redec

 decs/ stair lining make good decs GFL

 SH.G.07- make good bulkhead/ decorations

 SH.G.07-firestop services penetrations

 SH.2.09-firestop services penetrations