School House- scaffold almost struck- Ingrave Road
New RWP required with rodding access- within Hall SH.G.08
Ditto- route/ size to be reviewed with OR consulting on Mon 16.12
Phase II SH.G.09 works commenced
Ditto
Electrical containment strategy discussed to feed access control
Crack to Exams Office SH.1.11
Ditto- HRW to forward details of remedial works required
Opening formed, Door/ doorset ID.01.16 installed
Internal window to SH.1.10 blocked up
Door to SH.1.10 blocked in
Riser to SH.1.10 exposed
Stair 2 to plant area decorated- awaiting handrail
Smoke seal/ ironmongery/ signage to be fitted to cupboard door ID.02.05
SH.2.10 to be completed- decs etc.
Dado to Archive store SH.2.12 to be completed- walls/ ceiling touched in
cill to ID.01.08- diminishing strip required
Hoppers/ downpipe fitted to lightwell
Velux rooflights to top floor operational- awaiting fitting of blinds
Steel exposed to SH.G.15. Remdial works required to adjacent room SH.G.13