School House- scaffold almost struck- Ingrave Road

New RWP required with rodding access- within Hall SH.G.08

Ditto- route/ size to be reviewed with OR consulting on Mon 16.12

Phase II SH.G.09 works commenced

Ditto

Electrical containment strategy discussed to feed access control

Crack to Exams Office SH.1.11

Ditto- HRW to forward details of remedial works required

Opening formed, Door/ doorset ID.01.16 installed

Internal window to SH.1.10 blocked up

Door to SH.1.10 blocked in
Riser to SH.1.10 exposed
Stair 2 to plant area decorated- awaiting handrail

Smoke seal/ ironmongery/ signage to be fitted to cupboard door ID.02.05

SH.2.10 to be completed- decs etc.

Dado to Archive store SH.2.12 to be completed- walls/ ceiling touched in

cill to ID.01.08- diminishing strip required

Hoppers/ downpipe fitted to lightwell

Velux rooflights to top floor operational- awaiting fitting of blinds

Steel exposed to SH.G.15. Remdial works required to adjacent room SH.G.13