Conduit installation underway SH.1.06. Decorations to be completed/ touched in
Conduits/ lights SH.1.01.
SH.1.01. Decorations to be completed/ touched in
Stove blacking completed to SH.1.06
Lighting installation underway to SH.2.07
Dado trunking interface to be addressed SH.2.07
Ironmongery installation underway to SH.2.01
Rooflights 2FL. M&E to complete installation by securing Velux cable as per CVA/ OR comments
Decoration underway to SH.2.06
Conduits to landing SH.2.04.
Landing SH.2.04- decorations to be touched in to various locations
Stair 2/ SH.2.11- solid balustrade constructed.
Decorations required. Handrail to be fitted.
Overview from Ingrave Road. Scaffold roof struck. Lifts will gradually be reduced in coming week.
Ridge tile cracked- replace
Final flashings to be completed to roof
Window decorations underway to lightwell
Ridge flashing/ mortar bed to be completed
Underway to other ridge
Replace cracked tiles to valley
Replace defective tile to valley
Ensure valley tiling consistent with eaves tile installed to both faces full width
Ditto
Flashing to valley parapet- to be completed
Flashing to be completed to both ends
Hopper to be added to street side
Flashing to be installed street side- interface with parapet
Patination oil underway
Tuesday, 26 November 2013
Thursday, 21 November 2013
Site Visit 20.11.13
Roof to scaffold being removed
Lightning tapes awaiting pits for termination
Rainwater pipe/ drain run to be completed adjacent Barnards
Archive Room SH.2.12 decorations and carpet nearing completion
2nd fix electrical and decorations to be completed
Ditto
Ironmongery to cupboard generally still to be fitted
Nosings still to be removed to stair 2 to area within phase 1
Ditto
HR Office SH.2.10- docorations/ lining paper/ windows making good/ decoration to be completed.
Ditto
Sink + zip heater to SH.2.08 to be fitted 21.11.13
Windows to lightwell to be decorated
Remaining soft strip completed to Stair 2 2FL- decorations to be completed
Solid balustrade/ brick repairs to be carried out
Architrave/ decorations to ID.3.01 required
Instruction issued for ID.01.05
Making good/ filling still requires rubbing down in some areas. JD to review further on site w/c 25.11.13
Widnows EW.01.04 +05 still require decorations internally
Fire alarm cable- B&H to resolve disconnection issue/ temporary alarm to Stair 1 for duration of phase II
SH.1.06 Deputy Head's Office- decorations to boxings/ linings to be completed.
Conduit detail to bulkhead- touching in decorations still required
SH.1.01 decorations to boxing still required
Stove blacking/ chimney sock installation still to be carried out
SH.1.01. Electrical 2nd fix and final decorations required
Stair decorations underway. Pattress to new Part M compliant handrail completed- details discussed.
Sample of sikkens approved to all exposed timbers. Darker shade suggested.
Caulking to perimeter architrave/ completion of decorations required to all windows to dormers 2nd floor.
Stair 1 SH.2.03- guarding to be fitted. Rooflight 2nd fix electrical required.
Lightning tapes awaiting pits for termination
Rainwater pipe/ drain run to be completed adjacent Barnards
Firestopping required to services penetrations
2nd fix electrical and decorations to be completed
Ditto
Ironmongery to cupboard generally still to be fitted
Nosings still to be removed to stair 2 to area within phase 1
Ditto
HR Office SH.2.10- docorations/ lining paper/ windows making good/ decoration to be completed.
Ditto
Sink + zip heater to SH.2.08 to be fitted 21.11.13
Windows to lightwell to be decorated
Remaining soft strip completed to Stair 2 2FL- decorations to be completed
Solid balustrade/ brick repairs to be carried out
Architrave/ decorations to ID.3.01 required
Instruction issued for ID.01.05
Making good/ filling still requires rubbing down in some areas. JD to review further on site w/c 25.11.13
Widnows EW.01.04 +05 still require decorations internally
Fire alarm cable- B&H to resolve disconnection issue/ temporary alarm to Stair 1 for duration of phase II
SH.1.06 Deputy Head's Office- decorations to boxings/ linings to be completed.
Conduit detail to bulkhead- touching in decorations still required
SH.1.01 decorations to boxing still required
Stove blacking/ chimney sock installation still to be carried out
SH.1.01. Electrical 2nd fix and final decorations required
Stair decorations underway. Pattress to new Part M compliant handrail completed- details discussed.
Sample of sikkens approved to all exposed timbers. Darker shade suggested.
Caulking to perimeter architrave/ completion of decorations required to all windows to dormers 2nd floor.
Stair 1 SH.2.03- guarding to be fitted. Rooflight 2nd fix electrical required.