Lightning tapes awaiting pits for termination
Rainwater pipe/ drain run to be completed adjacent Barnards
Firestopping required to services penetrations
2nd fix electrical and decorations to be completed
Ditto
Ironmongery to cupboard generally still to be fitted
Nosings still to be removed to stair 2 to area within phase 1
Ditto
HR Office SH.2.10- docorations/ lining paper/ windows making good/ decoration to be completed.
Ditto
Sink + zip heater to SH.2.08 to be fitted 21.11.13
Windows to lightwell to be decorated
Remaining soft strip completed to Stair 2 2FL- decorations to be completed
Solid balustrade/ brick repairs to be carried out
Architrave/ decorations to ID.3.01 required
Instruction issued for ID.01.05
Making good/ filling still requires rubbing down in some areas. JD to review further on site w/c 25.11.13
Widnows EW.01.04 +05 still require decorations internally
Fire alarm cable- B&H to resolve disconnection issue/ temporary alarm to Stair 1 for duration of phase II
SH.1.06 Deputy Head's Office- decorations to boxings/ linings to be completed.
Conduit detail to bulkhead- touching in decorations still required
SH.1.01 decorations to boxing still required
Stove blacking/ chimney sock installation still to be carried out
SH.1.01. Electrical 2nd fix and final decorations required
Stair decorations underway. Pattress to new Part M compliant handrail completed- details discussed.
Sample of sikkens approved to all exposed timbers. Darker shade suggested.
Caulking to perimeter architrave/ completion of decorations required to all windows to dormers 2nd floor.
Stair 1 SH.2.03- guarding to be fitted. Rooflight 2nd fix electrical required.