Tuesday, 5 November 2013

Site Visit 04.11.13

Basement- ceiling lining- 2 layers plasterboard- to be completed.

Gas pipe to be vented- 2 No. vents. Water pipe to be boxed in- hatch for stopcock

Pump installed- connection still required

Secondary glazing installed to upper floors of former flat

Cornice reinstated adjacent lined steel

Doors awaiting seals 1FL offices

Secondary glazing to rear elevation- 1 No. unit to stair still to be fitted

Increase to level of balustrade- installation due 05.11.13

Radius to apex of lining internally to 2FL offices

SH.2.07- plaster complete

SH.2.06- awaiting plaster

Dormers awaiting render to cheeks

Tile breakages to be addressed. 22 No.

SH.2.02 plastering completed. Access rooflight to be installed after roofing works completed

SH.2.01- plastering underway

Fire lining required externally to staff room window- CVA to check allowance in contract

RWP/ below ground drainage to Barnards manhole- CVA to check provision/ instruction

CVA to forward revised lining detail where tray projects beyond wall

Archive room- decorations underway

trunking installation poor- archive room SH.2.12

Brick doctor required to solid balustrade- 2FL SH.2.11- CVA to instruct repairs

Wall to be built to tank room

Electrical track installed in wrong location- not approved- SH.2.11

Decorations to windows to lightwell to be carried out

Decoration/ making good/ prep all poor SH.2.11 corridor/ landing

Conduits/ redundant services to all be removed- SH.2.11

SH.G.06 redundant distribution not stripped out. CVA to instruct extended bulkhead

Phase 1 to complete at foot of stair with carpet/ decorations/ nosings

Mastic to perimeter of vinyl still required to WC SH.G.02

Bulkhead formed to foot of stair SH.G.04

Fireplace surround to SH.1.02 made good

Dado trunking detail poor/ poorly fitted where interface with skirting

Ditto

Parapet to be raised to accommodate flashing- both ends- CVA to instruct.

Ditto. Valley tiling/ lead valley nearing completion

Velux rooflights/ flashings nearing completion to valley

Velux rooflight to valley

Plastering 2FL

2FL Landing with new rooflight. Awaiting plastering/ trims to interfaces with hardboard/ architraves.