Ditto
Dormers complete- render panel complete
tiles to be cleaned of render/ bird faeces
Ditto
Mastic pointing of junction required to dormers
Tiling over dormer
Snow catcher- CVA to propose removal and replacement of gutter. Fascia to be replaced as part of original scope- see CVA DWG 0345.DE.15.1
Awaiting terracotta capping to parapet
Dormer to refurb tile roof
Gutter awaiting mastic to flashing
Ditto
Awaiting terracotta capping
Ditto- Also mortar to cover flashing required high level
More render required to recess where flashing over- check all dormers
Awaiting capping
Access rooflight installation underway. Tiles to head to be adjusted
Tile battens to be trimmed so no timber exposed beyond tiles. 4 No. locations to roof valley
Dry fix ridge tile termination/ interface with chimney. End section to be mortared
Roof valley overview. HCL safety system to be completed.
Gutter to be replaced- extended further/ larger radius due to new level of tiles following installation of ventilator beneath.
Snowcatcher to be removed. Fascia to be replaced as CVA DWG 0345 DE.15.1
Ditto
Galvanised conduit to SH.1.06 beneath bulkhead. Configuration varies from agreed detail but accepted by CVA.
New fireplace surround to SH.1.05
Waste pipe from High level tank now removed- SH.2.09. Decorations to be completed
SH.2.09- Stair decorations to be completed. Solid balustrade to be constructed. Brick repairs to be carried out.
Secondary glazing to EW.01.03 now installed
Hatch to corridor SH.G.04 made good with hardboard/ beading.
Trunking to SH.2.12- poor fitting to interfaces
Trunking to SH.2.12- poor fitting to changes in direction/ mitred cuts
Redundant socket to be removed SH.2.09. To be made good/ decorations
Sample Sikkens/ emulsion alternative decoration underway- for client review at progress meeting 20.11.13