Tuesday, 26 November 2013

Site Visit 25.11.13

 Conduit installation underway SH.1.06. Decorations to be completed/ touched in

 Conduits/ lights SH.1.01.

 SH.1.01. Decorations to be completed/ touched in

 Stove blacking completed to SH.1.06

 Lighting installation underway to SH.2.07

 Dado trunking interface to be addressed SH.2.07

 Ironmongery installation underway to SH.2.01

 Rooflights 2FL. M&E to complete installation by securing Velux cable as per CVA/ OR comments

 Decoration underway to SH.2.06

 Conduits to landing SH.2.04.

 Landing SH.2.04- decorations to be touched in to various locations

 Stair 2/ SH.2.11- solid balustrade constructed.

Decorations required. Handrail to be fitted.

 Overview from Ingrave Road. Scaffold roof struck. Lifts will gradually be reduced in coming week.

 Ridge tile cracked- replace

 Final flashings to be completed to roof

 Window decorations underway to lightwell

 Ridge flashing/ mortar bed to be completed

 Underway to other ridge

 Replace cracked tiles to valley

 Replace defective tile to valley

 Ensure valley tiling consistent with eaves tile installed to both faces full width

 Ditto

 Flashing to valley parapet- to be completed

Flashing to be completed to both ends

 Hopper to be added to street side

 Flashing to be installed street side- interface with parapet

Patination oil underway