Exam Papers Store SH.1.10- removeable panel to duct
Make good to wall
Smoke detectors to be added before SH.1.10 complete
SH1.11- architrave over door to be modified- trimmed down picture rail not fitted as discussed
Smoke detectors to be added before SH.1.11 complete
Touch in decorations to door closer to SH.1.10
CVA to discuss additional glazing with client- EW.1.10
CBD to accounts archive to be completed- inc. ironmongery to door ID.02.07
Toilet roll holder to SH.2.08 to be removed- school to replace
Gradus nosings- exposed cut end to winders. CVA to review with Gradus/ B&H
Scaffold to School House now erected around bay window
Tuesday, 21 January 2014
Thursday, 16 January 2014
Site Visit 15.1.14
Junction to SH.G.09 dado trunking. B&H to add mastic to junction where out of square
B&H to make good ceiling following services disconnection
Ditto
Reprographics sign to be replaced- spelling mistake
Wallpaper stripping underway to SH.G.09
Awaiting matwell to corridor SH.G.04
Architrave to be fitted to ID.00.04
Redundant controls/ lighting to be removed to corridor SH.G.04
Cupboard to be fitted to SH.G.06
Redundant switching to be removed to corridor SH.G.04
Lights to be cleaned/ relamped to SH.G.15 Paper store
Fire stopping required high level to services in corridor SH.G.16
Electrical works to be completed in SH.2.12 Accounts Archive- already handed over- board interfacing with some phase II elements
Existing dado to be removed to Communications ESH.1.01
Redundant cables awaiting removal/ making good to Stair 2 2FL
Boxing out following removal of redundant electrical services to Stair 2
Cleaning of gutter to be carried out to lightwell
CVA to liaise with school regarding replacemet of toilet roll holder
B&H to remove live material/ make good where water ingress to communications ESH.1.01 high level
Glass to be removed- clear/ film replaced to EW.1.09 and EW.1.18
CVA to liaise with school regarding replacement of glass to EW.1.10
School gutter repair to be carried out outside ESH.1.01
Slab repair to be carried out to area adjacent prior to hard landscape works
Weatherboard/ bulkhead to be constructed to courtyard SH.G.17
Door to plant to be replaced
B&H to make good ceiling following services disconnection
Ditto
Reprographics sign to be replaced- spelling mistake
Wallpaper stripping underway to SH.G.09
Awaiting matwell to corridor SH.G.04
Architrave to be fitted to ID.00.04
Redundant controls/ lighting to be removed to corridor SH.G.04
Cupboard to be fitted to SH.G.06
Redundant switching to be removed to corridor SH.G.04
Lights to be cleaned/ relamped to SH.G.15 Paper store
Fire stopping required high level to services in corridor SH.G.16
Electrical works to be completed in SH.2.12 Accounts Archive- already handed over- board interfacing with some phase II elements
Existing dado to be removed to Communications ESH.1.01
Redundant cables awaiting removal/ making good to Stair 2 2FL
Boxing out following removal of redundant electrical services to Stair 2
Cleaning of gutter to be carried out to lightwell
CVA to liaise with school regarding replacemet of toilet roll holder
B&H to remove live material/ make good where water ingress to communications ESH.1.01 high level
Glass to be removed- clear/ film replaced to EW.1.09 and EW.1.18
CVA to liaise with school regarding replacement of glass to EW.1.10
School gutter repair to be carried out outside ESH.1.01
Slab repair to be carried out to area adjacent prior to hard landscape works
Weatherboard/ bulkhead to be constructed to courtyard SH.G.17
Door to plant to be replaced
Monday, 13 January 2014
Site photos East School House- ESH 1.01
External wall adjacent comms cupboard- at high level.
Damp patch in location of leaking gutter externally
Adjacent wall
Detail of damp patch/ plaster
Damp patch in location of leaking gutter externally
Adjacent wall
Detail of damp patch/ plaster
Tuesday, 7 January 2014
Thursday, 2 January 2014
Site Visit 20.12.13
Structural ties inserted to SH.1.11 as instructed
Doors awaiting smoke seals SH.1.11
New door opening formed. Trim piece to architrave required- reuse existing picture rail
Maker good trim to hatch high level in ESH.1.01
M&E solutions to forward drawings regarding contractors proposals- containment routes to ESH.1.01 in relation to windows shown
Windows to be decorated- instruction to be raised if not included in scope
Scaffold struck- to be rebuilt around bay window from 6th Jan
Film to be added to GFL windows as scheduled. Also to basement clerestory light. Listed building consent applied for minor blocking in of opening as HRW sketch.
Tiles require replacement to lay in grid ceiling GFL- SH.G.16
Ceiling nearing completion to SH.G.06
Board to be switched over and full height cupboard installed to SH.G.06
Crack to wall SH.1.10- to be made good
Communications Studio ESH.1.01- partitions now removed and single room formed
Awaiting M&E solutions containment drawings around windows/ radiators
Sink/ zip heater now fitted to SH.2.08
Awaiting smoke seals to cupboard door ID.2.05
Decorations/ making good required around containment to SH.2.10
SH.2.10- ironmongery fitted- awaiting smoke seal
Handrail still to be fitted to Access stair 2
Concrete to courtyard SH.G.17- breaking up underway
Ditto
Film to windows to be carried out.
Doors awaiting smoke seals SH.1.11
New door opening formed. Trim piece to architrave required- reuse existing picture rail
Maker good trim to hatch high level in ESH.1.01
M&E solutions to forward drawings regarding contractors proposals- containment routes to ESH.1.01 in relation to windows shown
Windows to be decorated- instruction to be raised if not included in scope
Scaffold struck- to be rebuilt around bay window from 6th Jan
Film to be added to GFL windows as scheduled. Also to basement clerestory light. Listed building consent applied for minor blocking in of opening as HRW sketch.
Tiles require replacement to lay in grid ceiling GFL- SH.G.16
Ceiling nearing completion to SH.G.06
Board to be switched over and full height cupboard installed to SH.G.06
Crack to wall SH.1.10- to be made good
Communications Studio ESH.1.01- partitions now removed and single room formed
Awaiting M&E solutions containment drawings around windows/ radiators
Sink/ zip heater now fitted to SH.2.08
Awaiting smoke seals to cupboard door ID.2.05
Decorations/ making good required around containment to SH.2.10
SH.2.10- ironmongery fitted- awaiting smoke seal
Handrail still to be fitted to Access stair 2
Concrete to courtyard SH.G.17- breaking up underway
Ditto
Film to windows to be carried out.