Tuesday, 21 January 2014

Site visit 20.01.14

 Exam Papers Store SH.1.10- removeable panel to duct

Make good to wall

Smoke detectors to be added before SH.1.10 complete

SH1.11- architrave over door to be modified- trimmed down picture rail not fitted as discussed

Smoke detectors to be added before SH.1.11 complete

Touch in decorations to door closer to  SH.1.10

CVA to discuss additional glazing with client- EW.1.10

CBD to accounts archive to be completed- inc. ironmongery to door ID.02.07

Toilet roll holder to SH.2.08 to be removed- school to replace

Gradus nosings- exposed cut end to winders. CVA to review with Gradus/ B&H

Scaffold to School House now erected around bay window

Thursday, 16 January 2014

Site Visit 15.1.14

 Junction to SH.G.09 dado trunking. B&H to add mastic to junction where out of square

 B&H to make good ceiling following services disconnection

 Ditto

 Reprographics sign to be replaced- spelling mistake

Wallpaper stripping underway to  SH.G.09

  Awaiting matwell to corridor SH.G.04

 Architrave to be fitted to ID.00.04

 Redundant controls/ lighting to be removed to corridor SH.G.04

 Cupboard to be fitted to SH.G.06

 Redundant switching to be removed to corridor SH.G.04

 Lights to be cleaned/ relamped to SH.G.15 Paper store

 Fire stopping required high level to services in corridor SH.G.16

 Electrical works to be completed in SH.2.12 Accounts Archive- already handed over- board interfacing with some phase II elements

 Existing dado to be removed to Communications ESH.1.01

Redundant cables awaiting removal/ making good to Stair 2 2FL

 Boxing out following removal of redundant electrical services to Stair 2

 Cleaning of gutter to be carried out to lightwell

 CVA to liaise with school regarding replacemet of toilet roll holder

 B&H to remove live material/ make good where water ingress to communications ESH.1.01 high level

 Glass to be removed- clear/ film replaced to EW.1.09 and EW.1.18

 CVA to liaise with school regarding replacement of glass to EW.1.10

 School gutter repair to be carried out outside ESH.1.01

 Slab repair to be carried out to area adjacent prior to hard landscape works

 Weatherboard/ bulkhead to be constructed to courtyard SH.G.17

Door to plant to be replaced

Monday, 13 January 2014

Site photos East School House- ESH 1.01

 External wall adjacent comms cupboard- at high level.
Damp patch in location of leaking gutter externally

 Adjacent wall

Detail of damp patch/ plaster

Tuesday, 7 January 2014

Thursday, 2 January 2014

Site Visit 20.12.13

 Structural ties inserted to SH.1.11 as instructed

 Doors awaiting smoke seals SH.1.11

 New door opening formed. Trim piece to architrave required- reuse existing picture rail

 Maker good trim to hatch high level in ESH.1.01

M&E solutions to forward drawings regarding contractors proposals- containment routes to ESH.1.01 in relation to windows shown

 Windows to be decorated- instruction to be raised if not included in scope

 Scaffold struck- to be rebuilt around bay window from 6th Jan

 Film to be added to GFL windows as scheduled. Also to basement clerestory light. Listed building consent applied for minor blocking in of opening as HRW sketch.

 Tiles require replacement to lay in grid ceiling GFL- SH.G.16

 Ceiling nearing completion to SH.G.06

 Board to be switched over and full height cupboard installed to SH.G.06

 Crack to wall SH.1.10- to be made good

 Communications Studio ESH.1.01- partitions now removed and single room formed



 Awaiting M&E solutions containment drawings around windows/ radiators

 Sink/ zip heater now fitted to SH.2.08

 Awaiting smoke seals to cupboard door ID.2.05

 Decorations/ making good required around containment to SH.2.10

 SH.2.10- ironmongery fitted- awaiting smoke seal

 Handrail still to be fitted to Access stair 2

 Concrete to courtyard SH.G.17- breaking up underway

 Ditto

Film to windows to be carried out.