Junction to SH.G.09 dado trunking. B&H to add mastic to junction where out of square
B&H to make good ceiling following services disconnection
Ditto
Reprographics sign to be replaced- spelling mistake
Wallpaper stripping underway to SH.G.09
Awaiting matwell to corridor SH.G.04
Architrave to be fitted to ID.00.04
Redundant controls/ lighting to be removed to corridor SH.G.04
Cupboard to be fitted to SH.G.06
Redundant switching to be removed to corridor SH.G.04
Lights to be cleaned/ relamped to SH.G.15 Paper store
Fire stopping required high level to services in corridor SH.G.16
Electrical works to be completed in SH.2.12 Accounts Archive- already handed over- board interfacing with some phase II elements
Existing dado to be removed to Communications ESH.1.01
Redundant cables awaiting removal/ making good to Stair 2 2FL
Boxing out following removal of redundant electrical services to Stair 2
Cleaning of gutter to be carried out to lightwell
CVA to liaise with school regarding replacemet of toilet roll holder
B&H to remove live material/ make good where water ingress to communications ESH.1.01 high level
Glass to be removed- clear/ film replaced to EW.1.09 and EW.1.18
CVA to liaise with school regarding replacement of glass to EW.1.10
School gutter repair to be carried out outside ESH.1.01
Slab repair to be carried out to area adjacent prior to hard landscape works
Weatherboard/ bulkhead to be constructed to courtyard SH.G.17
Door to plant to be replaced