Thursday, 16 January 2014

Site Visit 15.1.14

 Junction to SH.G.09 dado trunking. B&H to add mastic to junction where out of square

 B&H to make good ceiling following services disconnection

 Ditto

 Reprographics sign to be replaced- spelling mistake

Wallpaper stripping underway to  SH.G.09

  Awaiting matwell to corridor SH.G.04

 Architrave to be fitted to ID.00.04

 Redundant controls/ lighting to be removed to corridor SH.G.04

 Cupboard to be fitted to SH.G.06

 Redundant switching to be removed to corridor SH.G.04

 Lights to be cleaned/ relamped to SH.G.15 Paper store

 Fire stopping required high level to services in corridor SH.G.16

 Electrical works to be completed in SH.2.12 Accounts Archive- already handed over- board interfacing with some phase II elements

 Existing dado to be removed to Communications ESH.1.01

Redundant cables awaiting removal/ making good to Stair 2 2FL

 Boxing out following removal of redundant electrical services to Stair 2

 Cleaning of gutter to be carried out to lightwell

 CVA to liaise with school regarding replacemet of toilet roll holder

 B&H to remove live material/ make good where water ingress to communications ESH.1.01 high level

 Glass to be removed- clear/ film replaced to EW.1.09 and EW.1.18

 CVA to liaise with school regarding replacement of glass to EW.1.10

 School gutter repair to be carried out outside ESH.1.01

 Slab repair to be carried out to area adjacent prior to hard landscape works

 Weatherboard/ bulkhead to be constructed to courtyard SH.G.17

Door to plant to be replaced