Structural ties inserted to SH.1.11 as instructed
Doors awaiting smoke seals SH.1.11
New door opening formed. Trim piece to architrave required- reuse existing picture rail
Maker good trim to hatch high level in ESH.1.01
M&E solutions to forward drawings regarding contractors proposals- containment routes to ESH.1.01 in relation to windows shown
Windows to be decorated- instruction to be raised if not included in scope
Scaffold struck- to be rebuilt around bay window from 6th Jan
Film to be added to GFL windows as scheduled. Also to basement clerestory light. Listed building consent applied for minor blocking in of opening as HRW sketch.
Tiles require replacement to lay in grid ceiling GFL- SH.G.16
Ceiling nearing completion to SH.G.06
Board to be switched over and full height cupboard installed to SH.G.06
Crack to wall SH.1.10- to be made good
Communications Studio ESH.1.01- partitions now removed and single room formed
Awaiting M&E solutions containment drawings around windows/ radiators
Sink/ zip heater now fitted to SH.2.08
Awaiting smoke seals to cupboard door ID.2.05
Decorations/ making good required around containment to SH.2.10
SH.2.10- ironmongery fitted- awaiting smoke seal
Handrail still to be fitted to Access stair 2
Concrete to courtyard SH.G.17- breaking up underway
Ditto
Film to windows to be carried out.