Thursday, 2 January 2014

Site Visit 20.12.13

 Structural ties inserted to SH.1.11 as instructed

 Doors awaiting smoke seals SH.1.11

 New door opening formed. Trim piece to architrave required- reuse existing picture rail

 Maker good trim to hatch high level in ESH.1.01

M&E solutions to forward drawings regarding contractors proposals- containment routes to ESH.1.01 in relation to windows shown

 Windows to be decorated- instruction to be raised if not included in scope

 Scaffold struck- to be rebuilt around bay window from 6th Jan

 Film to be added to GFL windows as scheduled. Also to basement clerestory light. Listed building consent applied for minor blocking in of opening as HRW sketch.

 Tiles require replacement to lay in grid ceiling GFL- SH.G.16

 Ceiling nearing completion to SH.G.06

 Board to be switched over and full height cupboard installed to SH.G.06

 Crack to wall SH.1.10- to be made good

 Communications Studio ESH.1.01- partitions now removed and single room formed



 Awaiting M&E solutions containment drawings around windows/ radiators

 Sink/ zip heater now fitted to SH.2.08

 Awaiting smoke seals to cupboard door ID.2.05

 Decorations/ making good required around containment to SH.2.10

 SH.2.10- ironmongery fitted- awaiting smoke seal

 Handrail still to be fitted to Access stair 2

 Concrete to courtyard SH.G.17- breaking up underway

 Ditto

Film to windows to be carried out.