Ditto
Making good required to plaster/ decs
Phase II- Database Office SH.G.09- containment strategy discussed with M&E Solutions
RWP route/ outlet to be instructed to SH.G.08 high level. Historic leak/ no fall/ no rodding access to current high level pipe. CVA to instruct
RWP- to be replaced
Hopper high level to light well. Calc of rainwater into lightwell required- CVA
Redundant gas pipe to be removed to basement area
Ceiling nearing completion GFL SH.G.06 Director MIS. Switchover of power to happen after Weds 18th as connected to Reprographics
Ceiling- Ditto
Repair to pipe- Mech subcontractor to forward spec of pipe clamp-
Trunking to SH.2.12- still to be made good/ redundant cabling to be fully removed.