Site visit 16.12.13

 SH.G.07 Common Room Secretaries- Lighting rose/ cabling to be modified

Ditto

 
 Door decoration/ ironmongery/ closer/ signage to be completed asap- Phase I works incomplete

 Making good required to plaster/ decs

 Phase II- Database Office SH.G.09- containment strategy discussed with M&E Solutions

 RWP route/ outlet to be instructed to SH.G.08 high level. Historic leak/ no fall/ no rodding access to current high level pipe. CVA to instruct


 RWP- to be replaced

 Hopper high level to light well. Calc of rainwater into lightwell required- CVA

 Redundant gas pipe to be removed to basement area

 Ceiling nearing completion GFL SH.G.06 Director MIS. Switchover of power to happen after Weds 18th as connected to Reprographics

 Ceiling- Ditto

 Repair to pipe- Mech subcontractor to forward spec of pipe clamp-

Trunking to SH.2.12- still to be made good/ redundant cabling to be fully removed.