Site Visit 02.12.13

 Lining paper to cbd SH.1.06- make good/ redec

 Ditto
 Trunking SH.1.06- Make good dec/ mastic dado

 Reinstate carpet SH.1.06

 Radius to conduit/ bulkhead SH.1.06 to be rectified

 Decoration adjacent ID.01.19/ dado- complete

 Complete carpets 1st floor

 Ditto

 Remove redundant cables to picture rail SH.1.04

 SH.1.01- address mortar/ carpet tile/ skirting interface

 Cap dado adjacent fireplace SH.1.01

 Make good junctions to dado trunking SH.1.01

 Ditto

 SH.2.06- nearing completion

 SH.2.06- Mastic to boxing in
 SH.2.06- Complete decs adjacent dado/ door

SH.2.02- 2nd coat to rooflight lining  required

 SH.2.02-crack below purlin- M/G redec

 SH.2.02- dado interface- redo

  SH.2.02- Decorate behind purlin

 Temp alarm install phase I/ complete system phase II

 Complete Sikkens decorations to exposed purlins/ purlin props 2FL

 Install guarding SH.2.04

 Install handrail- Part M compliant- Stair 1

 Clip cables to rooflight- all 2FL

 All carpet/ nosings to stair 1 complete

 Make good decs to stair 1

 Exposed threads to conduit SH.2.04

 Complete ironmongery installation EW.01.05

 SH.1.05- install grille to wall

 SH.1.05-complete dado
 Ditto

 SH.1.05-complete door decs ID.01.04

 Stair 1 soffitt 1FL to GFL- make good/ redec

 decs/ stair lining make good decs GFL

 SH.G.07- make good bulkhead/ decorations

 SH.G.07-firestop services penetrations

 SH.2.09-firestop services penetrations