RL.02.06- CVA to discuss refurbishment options with client - considering current condition.
Ditto
SH.1.05- fireplace surround costs still required from B&H
SH.1.05- plastering complete- ceiling boarding complete- awaiting plastering
Ceiling patched in to SH.1.02
Bonding coat repairs complete to SH.1.06
Skim coat complete to SH.1.01
Skim coat complete to SH.1.06
Angle fitted to steel to valley- awaiting completion of rafters
Openings for rooflights/ access hatch complete to 2 FL
Ply sheathing material on site
ESH.1.05 decorations poor. Preparation inconsistent. Blind fittings not removed prior to decorations- new blinds to be fitted.
ESH.1.05window EW.01.12 to be reglazed
ESH.1.05 Crack repairs poor- to be redone.
Thursday, 26 September 2013
Thursday, 19 September 2013
Site Visit 18.09.13
New joinery installation underway- GFL door to SH.G.06
Awaiting steelwork to support beam- between SH.1.01 and SH.1.06
Remains of different ceilings to SH.1.05 removed in lieu of boarding
Steelwork/ bulkhead formed to SH.1.06
Steel installed to roof valley 2FL
Dormer construction underway to Ingrave Road side of 2FL
New rafters plumb- old rafters 'sagging'. Tile battens to compensate over dormer head with tiling
Steel to valley
Propping to Purlins
Temporary protection installed to limit dust/ debris
Plastering underway to Archive
Temporary tank for heating
Paper to be removed to ceiling to SH.2.10
Awaiting steelwork to support beam- between SH.1.01 and SH.1.06
Remains of different ceilings to SH.1.05 removed in lieu of boarding
Steelwork/ bulkhead formed to SH.1.06
Steel installed to roof valley 2FL
Dormer construction underway to Ingrave Road side of 2FL
New rafters plumb- old rafters 'sagging'. Tile battens to compensate over dormer head with tiling
Steel to valley
Propping to Purlins
Temporary protection installed to limit dust/ debris
Plastering underway to Archive
Temporary tank for heating
Paper to be removed to ceiling to SH.2.10
Scaffold erected to lightwell for brickwork repairs/ window decorations
Wednesday, 11 September 2013
Site Visit 10.09.13
Timber plate/ rafters installed at 2FL
Ditto
Possible water ingress to HR Office SH.2.10- B&H to advise
TRV installation underway- redundant electrical services to be removed SH.1.08
Accounts Archive SH.2.12- plastering underway
SH.2.12- notching as HRW spec.
Decoration to windows EW.01.21,22,23,24+ EW.2.03,04,05 to require removal of glazed canopy panels to enable construction of tower. B&H to work up method statement.
Decorations to SH.G.07 Common Room Secretaries Office carried out but lighting replacement not complete
Decorations to WC SH.G.02- All surfaces to be adequately prepared/ cleaned as specification prior to decoration
Padstones to 2FL roof installed
Brickwork now tied to 2FL spine wall
Steelwork to valley on site- awaiting installation
Padstone 2FL- awaiting steel installation
Ditto
Ditto
TRV installation underway- redundant electrical services to be removed SH.1.08
Accounts Archive SH.2.12- plastering underway
SH.2.12- notching as HRW spec.
Decoration to windows EW.01.21,22,23,24+ EW.2.03,04,05 to require removal of glazed canopy panels to enable construction of tower. B&H to work up method statement.
Decorations to SH.G.07 Common Room Secretaries Office carried out but lighting replacement not complete
Decorations to SH.G.07 Common Room Secretaries Office carried out- blinds to be replaces therefore all existing clips etc to be removed before decoration.
Floor finishes to WC SH.G.02- Mastic seal to perimeter incompleteDecorations to WC SH.G.02- All surfaces to be adequately prepared/ cleaned as specification prior to decoration
Padstones to 2FL roof installed
Brickwork now tied to 2FL spine wall
Steelwork to valley on site- awaiting installation
Padstone 2FL- awaiting steel installation
Thursday, 5 September 2013
Site Visit 04.09.13
Suspended lay in grid ceiling to SH.G.06 should be removed and new internal bulkhead constructed. Ongoing decorations therefore incomplete. New lighting to be installed to this ceiling also. Refer GA.10.0 rev 1
Paint to radiators should be radiator paint as M60/ 130B and Decoration Schedule 46.1 rev0 (sample to be approved)
Redundant sockets to SH.G.06 and in general to be removed and walls/ surfaces made good PRIOR to decoration
Beam to SH.G.07 lined
Ceiling paper to be made good prior to redecoration
Ceiling to Common Room Secretaries office- Area requires heavy repair- Refer GA.10.0 rev 1
Fireplace to SH.1.02. CVA to schedule any additional repairs required to 1FL fireplaces for BH costing
Dividing wall between SH.1.01 and SH.1.02 to receive structural works as HRW spec.
Fireplace to SH.1.06
Fireplace to SH.1.01
Fireplace to SH.1.01- hearth works required
Ceiling to SH.2.10- paper to be removed and plaster refurbished. CVA to request cost/ issue AI as req'd
Paint to radiators should be radiator paint as M60/ 130B and Decoration Schedule 46.1 rev0 (sample to be approved)
Redundant sockets to SH.G.06 and in general to be removed and walls/ surfaces made good PRIOR to decoration
Beam to SH.G.07 lined
Ceiling paper to be made good prior to redecoration
Ceiling to Common Room Secretaries office- Area requires heavy repair- Refer GA.10.0 rev 1
Fireplace to SH.1.02. CVA to schedule any additional repairs required to 1FL fireplaces for BH costing
Dividing wall between SH.1.01 and SH.1.02 to receive structural works as HRW spec.
Fireplace to SH.1.06
Fireplace to SH.1.01
Fireplace to SH.1.01- hearth works required
Ceiling to SH.2.10- paper to be removed and plaster refurbished. CVA to request cost/ issue AI as req'd