Ditto
Ditto
TRV installation underway- redundant electrical services to be removed SH.1.08
Accounts Archive SH.2.12- plastering underway
SH.2.12- notching as HRW spec.
Decoration to windows EW.01.21,22,23,24+ EW.2.03,04,05 to require removal of glazed canopy panels to enable construction of tower. B&H to work up method statement.
Decorations to SH.G.07 Common Room Secretaries Office carried out but lighting replacement not complete
Decorations to SH.G.07 Common Room Secretaries Office carried out- blinds to be replaces therefore all existing clips etc to be removed before decoration.
Floor finishes to WC SH.G.02- Mastic seal to perimeter incompleteDecorations to WC SH.G.02- All surfaces to be adequately prepared/ cleaned as specification prior to decoration
Padstones to 2FL roof installed
Brickwork now tied to 2FL spine wall
Steelwork to valley on site- awaiting installation
Padstone 2FL- awaiting steel installation