Wednesday, 11 September 2013

Site Visit 10.09.13

Timber plate/ rafters installed at 2FL

 Ditto





 Ditto


Possible water ingress to HR Office SH.2.10- B&H to advise

TRV installation underway- redundant electrical services to be removed SH.1.08

Accounts Archive SH.2.12- plastering underway

SH.2.12- notching as HRW spec.

Decoration to windows EW.01.21,22,23,24+ EW.2.03,04,05 to require removal of glazed canopy panels to enable construction of tower. B&H to work up method statement.

Decorations to SH.G.07 Common Room Secretaries Office carried out but lighting replacement not complete

Decorations to SH.G.07 Common Room Secretaries Office carried out- blinds to be replaces therefore all existing clips etc to be removed before decoration.
Floor finishes to WC SH.G.02- Mastic seal to perimeter incomplete

Decorations to WC SH.G.02- All surfaces to be adequately prepared/ cleaned as specification prior to decoration
Padstones to 2FL roof installed

Brickwork now tied to 2FL spine wall


Steelwork to valley on site- awaiting installation


Padstone 2FL- awaiting steel installation