RL.02.06- CVA to discuss refurbishment options with client - considering current condition.
Ditto
SH.1.05- fireplace surround costs still required from B&H
SH.1.05- plastering complete- ceiling boarding complete- awaiting plastering
Ceiling patched in to SH.1.02
Bonding coat repairs complete to SH.1.06
Skim coat complete to SH.1.01
Skim coat complete to SH.1.06
Angle fitted to steel to valley- awaiting completion of rafters
Openings for rooflights/ access hatch complete to 2 FL
Ply sheathing material on site
ESH.1.05 decorations poor. Preparation inconsistent. Blind fittings not removed prior to decorations- new blinds to be fitted.
ESH.1.05window EW.01.12 to be reglazed
ESH.1.05 Crack repairs poor- to be redone.