Thursday, 26 September 2013

Site visit 25.09.13

 RL.02.06- CVA to discuss refurbishment options with client - considering current condition.

 Ditto

 SH.1.05- fireplace surround costs still required from B&H

  SH.1.05- plastering complete- ceiling boarding complete- awaiting plastering

 Ceiling patched in to SH.1.02

 Bonding coat repairs complete to SH.1.06

 Skim coat complete to SH.1.01

  Skim coat complete to SH.1.06

 Angle fitted to steel to valley- awaiting completion of rafters

 Openings for rooflights/ access hatch complete to 2 FL

 Ply sheathing material on site

 ESH.1.05 decorations poor. Preparation inconsistent. Blind fittings not removed prior to decorations- new blinds to be fitted.
  ESH.1.05window EW.01.12 to be reglazed

 ESH.1.05  Crack repairs poor- to be redone.