Thursday, 19 September 2013

Site Visit 18.09.13

 New joinery installation underway- GFL door to SH.G.06

 Awaiting steelwork to support beam- between SH.1.01 and SH.1.06


Remains of different ceilings to SH.1.05 removed in lieu of boarding

 Steelwork/ bulkhead formed to SH.1.06

 Steel installed to roof valley 2FL

 Dormer construction underway to Ingrave Road side of 2FL

 New rafters plumb- old rafters 'sagging'. Tile battens to compensate over dormer head with tiling

 Steel to valley

 Propping to Purlins

 Temporary protection installed to limit dust/ debris

 Plastering underway to Archive

 Temporary tank for heating


 Paper to be removed to ceiling to SH.2.10


Scaffold erected to lightwell for brickwork repairs/ window decorations