Awaiting steelwork to support beam- between SH.1.01 and SH.1.06
Remains of different ceilings to SH.1.05 removed in lieu of boarding
Steelwork/ bulkhead formed to SH.1.06
Steel installed to roof valley 2FL
Dormer construction underway to Ingrave Road side of 2FL
New rafters plumb- old rafters 'sagging'. Tile battens to compensate over dormer head with tiling
Steel to valley
Propping to Purlins
Temporary protection installed to limit dust/ debris
Plastering underway to Archive
Temporary tank for heating
Paper to be removed to ceiling to SH.2.10
Scaffold erected to lightwell for brickwork repairs/ window decorations