Thursday, 21 November 2013

Site Visit 20.11.13

 Roof to scaffold being removed

 Lightning tapes awaiting pits for termination

 Rainwater pipe/ drain run to be completed adjacent Barnards


Firestopping required to services penetrations 

 Archive Room SH.2.12 decorations and carpet nearing completion

 2nd fix electrical and decorations to be completed

 Ditto

 Ironmongery to cupboard generally still to be fitted

 Nosings still to be removed to stair 2 to area within phase 1

 Ditto
 HR Office SH.2.10- docorations/ lining paper/ windows making good/ decoration to be completed.

 Ditto

 Sink + zip heater to SH.2.08 to be fitted 21.11.13

 Windows to lightwell to be decorated

 Remaining soft strip completed to Stair 2 2FL- decorations to be completed

 Solid balustrade/ brick repairs to be carried out

 Architrave/ decorations to ID.3.01 required

 Instruction issued for ID.01.05

 Making good/ filling still requires rubbing down in some areas. JD to review further on site w/c 25.11.13

 Widnows EW.01.04 +05 still require decorations internally

Fire alarm cable- B&H to resolve disconnection issue/ temporary alarm to Stair 1 for duration of phase II
 SH.1.06 Deputy Head's Office- decorations to boxings/ linings to be completed.

 Conduit detail to bulkhead- touching in decorations still required

 SH.1.01 decorations to boxing still required

 Stove blacking/ chimney sock installation still to be carried out

 SH.1.01. Electrical 2nd fix and final decorations required

 Stair decorations underway. Pattress to new Part M compliant handrail completed- details discussed.

 Sample of sikkens approved to all exposed timbers. Darker shade suggested.

Caulking to perimeter architrave/ completion of decorations required to all windows to dormers 2nd floor.

Stair 1 SH.2.03- guarding to be fitted. Rooflight 2nd fix electrical required.

2 comments: