Plastering skim coat to Accounts Archive SH.2.12
Ditto
Builderswork/ electrical containment route underway high level 2nd floor
HR Office mist coat completed but redundant cables/ services require removal
Ditto
Ditto
Where TRV fittted cill poorly cut- to be rectified
Window refurbishment to be completed
Rafters and purlin prop require decoration following plasterboard lining completion. CVA to forward proposal
Valley beam steel/ timber connections
Felt/ battening underway
Gutter requires amended kerb adjacent parapet. Overall height from lowest level of gutter should be 150mm minimum and upstand formed in 18mm as K11/ 515A. Asphalt/ kerb to be independent of parapet wall by 10mm as in clause K11/515A. Lead flashing to be dressed over- thermal movement to be allowed between two structures. Contractor to amend prior to an further leadwork.
Ditto
Internal frame of dormer
External ply cladding to dormer
Dormer detail awaiting lead
GFL- electrical containment extends beyond line of wall above/. External weatherboarding detail to be amended to accommodate. 90 degree turns at limits.
GFL Lobby SH.G.16 ceiling to be amended to accommodate revised electrical services opening/ route to left hand side of existing heating pipework.
Outlet location to be amended in accordance with LSA.
Awaiting hopper to 2FL outlet through wall