Tuesday, 15 October 2013

Site Visit 14.10.13

 1st fix electrical tray/ builderswork

 Plastering skim coat to Accounts Archive SH.2.12

 Ditto

Builderswork/ electrical containment route underway high level 2nd floor

 HR Office mist coat completed but redundant cables/ services require removal

 Ditto

 Ditto

 Where TRV fittted cill poorly cut- to be rectified

 Window refurbishment to be completed

Rafters and purlin prop require decoration following plasterboard lining completion. CVA to forward proposal

Valley beam steel/ timber connections

  Felt/ battening underway


Gutter requires amended kerb adjacent parapet. Overall height from lowest level of gutter should be 150mm minimum and upstand formed in 18mm as K11/ 515A. Asphalt/ kerb to be independent of parapet wall by 10mm as in clause K11/515A. Lead flashing to be dressed over- thermal movement to be allowed between two structures. Contractor to amend prior to an further leadwork.

Ditto
 

 Internal frame of dormer

 External ply cladding to dormer

 Dormer detail awaiting lead

 GFL- electrical containment extends beyond line of wall above/. External weatherboarding detail to be amended to accommodate. 90 degree turns at limits.

 GFL Lobby SH.G.16 ceiling to be amended to accommodate revised electrical services opening/ route to left hand side of existing heating pipework.

 Outlet location to be amended in accordance with LSA.

Awaiting hopper to 2FL outlet through wall