Awaiting bulkhead to be constructed- Director MIS office
6mm ply currently being fitted to 1FL offices
Cupboard door ironmongery difficult to fit- CVA to liaise with AC Leigh regarding their specification
Doors 1st floor routed in lieu of smoke seals
Cornice to be adjusted to ensure meeting at corner/ mitre
Windows to former flat now awaiting secondary glazing- all squaring of openings to be carried out by Selectaglaze. Decorations may need to be made good following installation.
Straps to 2FL roof installed- between rafters and flank walls
Purlin prop plates now installed to 2FL- roof structure
Ditto
Insulation installed between valley deck and valley steel as specified
Dormer flashings underway to Ingrave Road elevation
2FL spine wall- battens installed for drylining finish
Dormer flashing to rear elevation. Tiling awaiting completion/ render to cheeks to be completed
Dormer flashings- soakers awaiting render to cheeks over- render bead to be applied
Dormer lead detail
Existing leadwork adjacent chimney to be dressed back over lead soakers
Straps to spine wall 2FL
Valley awaiting flashing/ tiling.
Single outlet blocked- new outlets drilled- in compliance with lead sheet association recommendations
Back of lead dormer completed
2FL soft strip/ demolition completed. Stair opened up
TRVs required to radiators within archive room
Awaiting new solid balustrade detail to 2FL service stair
AC Leigh wired door access readers fitted