Bursar's office-  skirting to be cut back to allow trunking to be fixed directly to wall- to avoid existing floor joist.

Awaiting bulkhead to be constructed- Director MIS office

                                        
6mm ply currently being fitted to 1FL offices 

 Cupboard door ironmongery difficult to fit- CVA to liaise with AC Leigh regarding their specification

 Doors 1st floor routed in lieu of smoke seals

Cornice to be adjusted to ensure meeting at corner/ mitre

Windows to former flat now awaiting secondary glazing- all squaring of openings to be carried out by Selectaglaze. Decorations may need to be made good following installation.

 Straps to 2FL roof installed- between rafters and flank walls

 Purlin prop plates now installed to 2FL- roof structure

 Ditto

Insulation installed between valley deck and valley steel as specified

 
 Asphalt kerb now extended to 150mm height minimum- awaiting parapet flashing

 Dormer flashings underway to Ingrave Road elevation

 2FL spine wall- battens installed for drylining finish

 Dormer flashing to rear elevation. Tiling awaiting completion/ render to cheeks to be completed

 Dormer flashings- soakers awaiting render to cheeks over- render bead to be applied

 Dormer lead detail

 Existing leadwork adjacent chimney to be dressed back over lead soakers

 Straps to spine wall 2FL

 Valley awaiting flashing/ tiling.

 Single outlet blocked- new outlets drilled- in compliance with lead sheet association recommendations
 Back of lead dormer completed


2FL soft strip/ demolition completed. Stair opened up
 
 Damage to solid balustrade- to be made good prior to decoration

 TRVs required to radiators within archive room

 Awaiting new solid balustrade detail to 2FL service stair

AC Leigh wired door access readers fitted