Drylining to basement is underway. Ceiling to SH.B.04 & 05 to be insulated as per specification. Battens to be fixed to joists where required to create 50mm void.
Ceiling to SH.B.03 to be insulated as per specification.
Gas meter to SH.B.04 removal discussed – associated pipework obstructive to ceiling lining. OR to confirm contract requirements.
Pipework to SH.B.03 associated with gas meter. B&H to remove.
Stair & landing dry lining removed as part of asbestos removal works. Walls and stair
underside to be relined in plasterboard. Wall dividing basement stair and MIS Calender office to be insulated and lined in MDF. CVA to request costs
Stair treads above basement landing to be repaired prior to lining. CVA to request costs
Ditto
Plastering to SH.1.06 is complete
Ditto - steel boxing has been plastered. Cornice has not been reinstated.
Plastering to SH.1.05 is complete. Cornice to be reinstated.
Suspended ceiling and secondary plywood ceiling to corridor SH.G.04 to be removed to allow fixing ofcontainment route.
Concrete downstand in SH.G.16 above ID.00.10 prevents containment trays from being fixed at high level. Water pipes prevent containment trays dropping from high to low. OR to advise on Phase 3 coordination.
Parapet gutter to street facade has been constructed. To be lined in asphalt.
Dormer cheek ventillation gaps have been lined in insect mesh.
Ditto
Ditto
Plant room door to be 30 min fire rated with smoke seals. CVA to confirm whether frame provides suitable fire rating.