Monday, 24 February 2014

Site Visit 21.02.14

 Store SH.G.13. Existing cill raked. HRW to forward revised detail

Coping to bay window condemned. Coping to be redone. Cutting/ pointing/ overhang defective. B&H to recut/ reset.

 Ditto

Shoe required to downpipe- into gulley

 ED.00.03- Decoration still required

 Bulkhead to courtyard- COI required for boarding over of bulkhead.

 Paving to courtyard. Further cuts/ infill required to perimeter

 Bend/ shoe required for boiler condensate to new gulley

 Inset cover to manhole to be reset- currently trip hazard on fire escape route

 Remaining stray cables to be trimmed. loose felt to be trimmed above EW.1.04

 Brick pavers to be cleaned fully of cement/ debris

 Handrail now fitted to stair of Lobby ESH.1.02- COI to be raised

 Bulkhead to be completed with T&G/ shiplap as H21/ 110A. Additional lead flashing required over- COI required.
 CBD door ID.02.05- make good decs where escutcheon removed

 Cable to be removed following installation of new bell system

 Window EW.02.03 not decorated externally. Ditto EW.01.29, EW.01.30

 trunking/ redundant cables to be removed/ decorations made good to 2FL stair- Stair 2

 Ditto

 Basement- taping and jointing still required

 Ditto

 New nosings to timber access stair still to be fitted

 Photocopier in Disabled refuge area

IW.00.01- services penetration to be fire stopped- also fire-rated board over existing window- as raised by Fire Officer. COI to be raised if not part of original scope/ or if removed within contract.