No alarm interface to ED.00.08
Boxing in required to Salto box for security
ESH.G.07- Dado trunking already installed outside contract- therefore to be omitted from scope
Ditto
Intumescent strips required to Plant door ED.00.01. Door also sticking
New recessed manhole cover- setting/ infill to be redone- currently trip hazard on escape route
COI item- board over existing duct where pigeon nesting
Taping and jointing complete to Basement- awaiting hatch to gas meter location
Escape signage complete to basement
1 No. edge bead incomplete on stair to basement
New stair nosing required- to be fitted- basement stair
Redundant light fitting to Stair 1 SH.G.04 to be removed/ replaced with L4E emergency fitting
Nosings to be cut back/ burr removed to winder Stair 1 SH.G.05
School Bell to be removed/ replaced with other alarms in Chapel
Ditto- break glass to be removed/ sounder also/ decorations to be made good following chapel fire alarm installation
Window to SH.G.12- fireboard to be reinstated + fire batt/ intumescent foam around service penetrations- COI required
Conduit/ wall to be made good SH.G.09
Decorations to be made good where services removed- SH.1.07 adjacent ID.01.06
Ditto
Cable to be removed following chapel alarm installation. bulkhead to be made good adjacent conduit
Data faceplate complete to dado ESH.1.01
Make good conduit ESH.1.06
Ditto
Make good wall/ decs to meeting room