Friday, 28 February 2014

site visit 27.02.14

 No alarm interface to ED.00.08

 Boxing in required to Salto box for security

 ESH.G.07- Dado trunking already installed outside contract- therefore to be omitted from scope

 Ditto



 Intumescent strips required to Plant door ED.00.01. Door also sticking

 New recessed manhole cover- setting/ infill to be redone- currently trip hazard on escape route

 COI item- board over existing duct where pigeon nesting

 Taping and jointing complete to Basement- awaiting hatch to gas meter location

 Escape signage complete to basement

 1 No. edge bead incomplete on stair to basement

 New stair nosing required- to be fitted- basement stair

 Redundant light fitting to Stair 1 SH.G.04 to be removed/ replaced with L4E emergency fitting

 Nosings to be cut back/ burr removed to winder Stair 1 SH.G.05

 School Bell to be removed/ replaced with other alarms in Chapel

 Ditto- break glass to be removed/ sounder also/ decorations to be made good following chapel fire alarm installation

 Window to SH.G.12- fireboard to be reinstated + fire batt/ intumescent foam around service penetrations- COI required
 Conduit/ wall to be made good SH.G.09

 Decorations to be made good where services removed- SH.1.07 adjacent ID.01.06

 Ditto

 Cable to be removed following chapel alarm installation. bulkhead to be made good adjacent conduit

 Data faceplate complete to dado ESH.1.01

 Make good conduit ESH.1.06

 Ditto

Make good wall/ decs to meeting room