Shelf and cupboard to SH.G.01 to be cleared by school in lieu of making good/ decorations
HRW to advise regarding reinstatement of prop
Fireplace uncovered in Deputy Head Office SH.1.05. CVA to request cost for new surround and mantle to match existing adjacent
Lining paper removed to 1st floor offices. Repairs to plaster considerable
Ditto
2fl roof coverings removed. CVA to request cost for removing 2 No. redundant water tanks currently within loft spaces
Ditto
Existing valley gutter exposed- survey required by contractor/ steel fabricator for HRW review
Office SH.2.01- false walls requiring opening up in 2fl offices. CVA to request cost for removing
Meeting Room SH.2.07- ditto
Open lead chute gutter exposed to SH.2.07
Roof covering removed- rafters exposed and ceiling timbers removed
Mytons alternative staff bead- B&H to clarify variation from Ventrolla specification for CVA comments
Mytons alternative parting bead
Mytons alternative bead
Ceiling opening up reveals hole to GFL ceiling SH.G.06 Director MIS
Ditto
Existing valley gutter exposed
View into SH.2.07 from roof valley
Dormers- Ingrave Road side
Dormer frames rooten- no insulation
Ditto
Ground floor corridor SH.G.04. Stair 1 opened up.