Friday, 19 July 2013

Site Visit 18.07.13

 Common Room Secretaries Office SH.G.07 still to be cleared by school

 Shelf and cupboard to SH.G.01 to be cleared by school in lieu of making good/ decorations

 HRW to advise regarding reinstatement of prop

Fireplace uncovered in Deputy Head Office SH.1.05. CVA to request cost for new surround and mantle to match existing adjacent

 Lining paper removed to 1st floor offices. Repairs to plaster considerable

 Ditto

2fl roof coverings removed. CVA to request cost for removing 2 No. redundant water tanks currently within loft spaces
Ditto



Existing  valley gutter exposed- survey required by contractor/ steel fabricator for HRW review

Office SH.2.01-  false walls requiring opening up in 2fl offices. CVA to request cost for removing

Ditto Office SH.2.02

 
Meeting Room SH.2.07- ditto

 Open lead chute gutter exposed to SH.2.07

 Roof covering removed- rafters exposed and ceiling timbers removed

 Mytons alternative staff bead- B&H to clarify variation from Ventrolla specification for CVA comments

 Mytons alternative parting bead

 Mytons alternative bead

 Ceiling opening up reveals hole to GFL ceiling SH.G.06 Director MIS


 Ditto

 Existing valley gutter exposed

 View into SH.2.07 from roof valley

 Dormers- Ingrave Road side

 Dormer frames rooten- no insulation

 Ditto

Ground floor corridor SH.G.04. Stair 1 opened up.