Damp to carpet in SH.G.16 was investigated. Appears to be roof overflow. B&H to monitor during fair weather.
Ditto
Pad stone to steel in basement installed. Stone supported by engineering bricks and replacement bricks to spine wall.
Opening to basement wall created to allow material to be removed from basement during damp proofing works. Opening temporarily blocked.
Enabling works to be undertaken prior to second pad stone being installed in basement. Redundant pipe to be removed.
Re-plastering required where partition removed in SH.G.04. Door architrave to be made good.
Re-pairs to banister required where partition removed in SH.G.04. Sliced banister to be replaced to match existing.
Ditto
Hardboard panel to SH.1.02 to be removed and re-fixed to timbers installed behind.
Ditto
Window repairs to SH.1.02 are underway. Sashes are being made operable.
Cornice to ceiling to be removed prior to lining of ceiling in plasterboard.
Hardboard to fireplace has been removed. Re plastering to be carried out in cement bonded plaster. New timber fireplace surround to be specified by CVA.
Dormers have been removed at Level 2.
Internal partitions have been stripped where in poor condition.
Ditto
Rafters to dormers show signs of rot. B&H to confirm whether replacements will be required.
Ditto
Banister to stair has been damaged. Repair to form part of refurbishment works.
Spine wall has been stripped to allow for replastering.
Existing brickwork was surveyed for mortar mix, colour and pointing.
Ditto - pointing is not recessed on flank wall.
Downpipe to be removed. Penetration through parapet cornice to be reused for new parapet gutter outlet.
Gutter board to lead chute has been stripped.
Dormers have been removed
Gutter board has been removed in preparation for valley restructuring.
Brickwork to flank wall parapet is in poor condition. To be removed to allow pad stone and steel to be inserted.
Opening to front wall to basement to allow material to be removed as part of damp proofing works.
Ditto
Pad stone to steel in basement installed. Stone supported by engineering bricks and replacement bricks to spine wall.
Opening to basement wall created to allow material to be removed from basement during damp proofing works. Opening temporarily blocked.
Enabling works to be undertaken prior to second pad stone being installed in basement. Redundant pipe to be removed.
Re-plastering required where partition removed in SH.G.04. Door architrave to be made good.
Re-pairs to banister required where partition removed in SH.G.04. Sliced banister to be replaced to match existing.
Ditto
Hardboard panel to SH.1.02 to be removed and re-fixed to timbers installed behind.
Ditto
Window repairs to SH.1.02 are underway. Sashes are being made operable.
Cornice to ceiling to be removed prior to lining of ceiling in plasterboard.
Hardboard to fireplace has been removed. Re plastering to be carried out in cement bonded plaster. New timber fireplace surround to be specified by CVA.
Dormers have been removed at Level 2.
Internal partitions have been stripped where in poor condition.
Ditto
Rafters to dormers show signs of rot. B&H to confirm whether replacements will be required.
Ditto
Banister to stair has been damaged. Repair to form part of refurbishment works.
Spine wall has been stripped to allow for replastering.
Existing brickwork was surveyed for mortar mix, colour and pointing.
Ditto - pointing is not recessed on flank wall.
Downpipe to be removed. Penetration through parapet cornice to be reused for new parapet gutter outlet.
Gutter board to lead chute has been stripped.
Dormers have been removed
Gutter board has been removed in preparation for valley restructuring.
Brickwork to flank wall parapet is in poor condition. To be removed to allow pad stone and steel to be inserted.
Opening to front wall to basement to allow material to be removed as part of damp proofing works.