Friday, 2 August 2013

Site Visit 01.08.13


Roof tile samples. 
Top row from left to right: Reclaimed tile, Ashbury, Barfiled
Bottom row from left to right: Existing roof tile, Keymer Traditional Elizabethan, Keymer Traditional Wealden Red, Keymer Traditional Antique


Reclaimed Tile 

Ashbury

 Barfield
 
 Keymer Traditional Antique

 Keymer Traditional Wealden Red

 Keymer Traditional Elizabethan

  Existing roof tile

 Dormers to be demolished. Photo record of existing dormer fascia profile.

 North west chimney stack condition

 Chimney pots to South East chimney in cracked condition prior to reflanching

 Ditto

 Ditto

 Bricks to South East chimney require repair.

 Ditto - approx 6 brick faces to be repaired

 Ditto

Ditto

 Ditto

 Ditto

 Repointing required to all lower bricks

 Ditto & brick to be replaced at low level

 Areas requiring repointing and brick fascias to be repaired
 
 South West chimney stack requires less work - 2 brick faces repaired

 Ditto

 Repointing required to north lightwell wall. CVA to request costs/schedule as part of brick repairs.
 Ditto


 Valley gutter has been stripped to reveal gutter board

 Repointing to west facade where Stress UK works have been signed off. Snowcem mortar with has been used. Still drying out.

 Lower sash to window EW.00.02 does not fit frame and requires replacement.
 
 All upper sashes to west (street) elevation have been built fixed shut. School to confirm that they do not require opening.


Upper and lower sashes to EW.1.02 have been fixed shut. Lower sash to be eased open. School to confirm requirements.


 Lower sash to EW.02.05 has rotten corner. Cost for splicing to be requested.

Internal and external frame to EW.02.05 is also rotten in both lower corners. Cost for splicing to be requested.
 Ditto
 
 Ditto
 
 Cill to EW.02.13 is rotten. Cost to be requested for repair.

 Demolition to corridor SH.G.04 are underway. Staircase has been opened up.

 Remaining bulkhead to be removed.

 Conservation have agreed to replacement of ID.01.21. CVA tor request approval of replacement with a 3 paneled door.

  Ditto - proposed door height to be in line with 6 paneled internal door behind. Panels to be aligned with door behind. Cornice fixed above. Conservation officer to review for approval.
 
 Additional plaster repairs are being scheduled by Bolt & Heeks. Conservation to approve the use of patch repair, bonding coat with skim. Walls to SH.1.05, Deputy Head Office: East.

 SH.1.05, North. Lath exposed - plastering mesh to be laid directly onto timber.

 SH.1.05, West.

 SH.1.05, South.

 SH.1.05, West - Tiles have been revealed beneath plaster. They are in poor condition and are very lose.

 SH.1.05, West - Ditto

 SH.1.06 Deputy Head Office: North

 SH.1.06 East

 SH.1.06 South

 SH.1.06 West

 SH.1.01 Second Master Office: North

 SH.1.01 East

 SH.1.01 South

 SH.1.01 West
 SH.1.01 South - Surface uneven above and below timber dado rail mount.

 SH.1.01 West -Patch repairs required where masonry revealed.

 SH.1.01 West - Repairs required to hearth. Conservation officer to advise

Ditto

 SH.1.02 Deputy Head Office - North


SH.1.02 East

 SH.1.02 South

 SH.1.02 West


Joinery has been revealed at Level 2: SH.2.02, Office -
Conservation to advise on whether joinery must be retained.

 SH.2.02 - HRW to check chimney structure

 SH.2.06 Office -
Conservation to advise on whether joinery must be retained.

 SH.2.06

 SH.2.07 Meeting room -
Conservation to advise on whether joinery must be retained.

 SH.2.07 lead chute gutter

 SH.2.01 Office - Conservation to advise on whether joinery must be retained.
  
 Lead chute gutter is visible behind gutter board

 Gutter board height varies - B&H to provide survey